Client:
Hudbay MineralsLocation:
Snow Lake, Manitoba, CanadaDuration:
4 YearsScope of Work:
Product:
Redbore 40, Redbore 50EDR, Redbore 70Underground ramp development and raiseboring
This underground ramp development project consisted of over 5,000 metres of down ramp and lateral development over a 4-year period.
The project scope also included 40 m of Alimak raising, 1,200 m of 3.05 m Ø raiseboring and various construction activities.
Redbore 40 work consisted of 48” diameter production raises, service holes and paste fill holes with pipe installation.
Production slots and service holes were completed with the Redbore 50ERD, while the Redbore 70 carried out the ventilation raises.
;